Project Center



Client:  U.S. Army Corps of Engineers Construction Research Engineering Laboratory
Waste Treated:  Deconstruction Materials Contaminated with Lead Based Paint
Project Initiated:  February, 2003
Project Completed:  November, 2003
Project Goal:  Remove, Recover and Recycle Lead from Salvaged Building Materials Contaminated with Lead Based Paint

ARI conducted a demonstration on military deconstruction materials contaminated with lead-based paint for the U.S. Army Engineer Research & Development Center – Construction Engineering Research Laboratory (ERDC/CERL), under a contract with the Naval Facilities Engineering Service Center (NFESC).

The tests showed that ARI’s technology results in a 97% volume reduction and a 90% reduction in the mass of the material. The lead contained in the material was captured and concentrated into a product containing up to 25% lead in form suitable for recycling.

The data produced from the tests facilitated the development of a design of a transportable processing system for the LBP-coated materials. The transportable processing system can process the waste for a cost of less than 1/3 the cost of land disposal of the waste designated as RCRA hazardous waste.

Return to Project Center

 

ARI Technologies, Inc. • 1221 2nd Avenue North • Kent, WA 98032 • USA
Phone: 253.796.5995 • FAX: 425.961.0632